Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Click The Gear button to set up the interval (fig 2)

Set the required gap, in days or in weeks, between the delivery dates (fig 3)

Switch on “Skip over weekends” if you want to refrain from setting delivery dates to weekend days (fig 4)

Info

If you switch off “Skip over weekends”, weekend days will be marked with pink frames after the dates will be entered to differentiate them from week days

Click Save and close to schedule the dates (fig 5)

...

This will be the result when “Skip over weekends is On.

Orders/tasks will not be scheduled on weekend days

...

This will be the result when “Skip over weekends is Off.

Orders/tasks will be scheduled on weekend days.

Weekend days will have a purple frame to differentiate them from week days

...

Scheduling Interval dates with “Paste”

...

Click The Gear button to set up the interval (fig 2 )

...

Set the required gap, in days or in weeks, between the delivery dates (fig 1)

Switch on “Skip over weekends” if you want the to refrain from setting delivery dates to weekend days (fig 2)

...