Expand | ||
---|---|---|
| ||
Support for supplier script has been added. With a supplier script, a different script type (with script, without script) can be used for different tasks. This will reflect itself in rate calculation.
|
Expand | ||
---|---|---|
| ||
From: Administrator > Web administrator > Configuration > Defaults tab A new option was added to the system: Change orders to 'In progress' once all pre-production tasks are completed If enabled (1), the status of orders will automatically change to “In progress”, making it visible to basic resources. Additional settings were also added to notify the resource in charge of the orders that the status was automatically changed (2). The standard task assignment notification can also be sent out for resources assigned to tasks within these orders (3).
| ||
Expand | ||
| ||
Expand | ||
|
Info |
---|
For a more detailed explanation, please check the Automatic notification of changes to a task section of the System notifications help desk article. |
...
title | Require resource reference - New system setting added (4950) |
---|
In Administrator > Configuration > Settings a new system setting was added to determine if resources must enter a reference number when submitting a Resource report.
Additionally, entering a reference number will no longer lock the report or it’s items for editing, only submitting it will do so.
...
title | Filtering and Order creation for multiple media numbers added to the range options (4757) |
---|
Using the range options, it’s now possible to filter for a specific list of media numbers.
This functionality is available within the range options page, and allows for the search of multiple media numbers at once.
...
| ||
Using the range options, it’s now possible to filter for a specific list of media numbers. This functionality is available within the range options page, and allows for the search of multiple media numbers at once.
|
Expand | ||
---|---|---|
| ||
From: Administrator > Web administrator > Configuration > Defaults tab A new option was added to the system: Change orders to 'In progress' once all pre-production tasks are completed If enabled (1), the status of orders will automatically change to “In progress”, making it visible to basic resources. Additional settings were also added to notify the resource in charge of the orders that the status was automatically changed (2). The standard task assignment notification can also be sent out for resources assigned to tasks within these orders (3).
|
Expand | ||
---|---|---|
| ||
A new option has been added to the system, enabling the user to check a resource’s availability or current assignments before assigning a task: The calendar shortcut will open the Team tasks manipulation scheduler and show the selected resource’s current assignments and more resources can be selected and compared. By clicking on “Assign (Name of resource)”, the resource will be assigned to the selected task. This functionality can be enabled from Administrator > Web administrator > Settings, using the “Display the scheduler in the resource assignment” option: |
Expand | ||
---|---|---|
| ||
It is now possible to send automatic notifications to resources if changes are applied to tasks they are assigned to: These notifications can be enabled from Administrator > Web administrator > Application configuration > Emails:
|
Expand | ||
---|---|---|
| ||
In Administrator > Configuration > Settings a new system setting was added to determine if resources must enter a reference number when submitting a Resource report. Additionally, entering a reference number will no longer lock the report or it’s items for editing, only submitting it will do so. |
Projects improvements
The “Projects” functionality has undergone multiple changes to improve usability:
...