To be able to assign a resource to tasks, some mandatory settings must be setup:
Setting resource skills.
Setting the “Cannot be assigned” switch
Setting the “Resource active” switch
Setting resource skills
make sure all the following attributes are correctly set:
Set the resources skills for task assignment. This will determine to which tasks
...
this resource can be assigned
...
Languages .
From: Manager > Rolodex tables > Resources > Magnifying glass > Skills for task assignment:
Languages or Language pairs (source and target)
...
the resource can be assigned to (Fig 1)
Task types
...
Order types he can do (Fig 3)
...
Setting the resources Languages skills:
Click on the Languages button (fig 1)
Enable / Disable the languages according to the resources skills (fig 2)
Click Close (fig 3)
Setting the resources Task types:
Click on the Tasks button (fig 1)
Enable / Disable the Task types according to the resources skills (fig 2)
Click Close (fig 3)
Setting the resources Order types:
...
Click on the Tasks button (fig 1)
...
the resource can be assigned to (Fig 2)
Order types the resource can be assigned to (
...
Fig 3)
...
Once the resources skills are set, only relevant resources will be displayed in the resource pull-down menu when assigning resources to tasks.
Setting the “Cannot be assigned” switch
Note |
---|
Without setting these skills, the resource cannot be assigned to any task |
...
2. Make sure the “Cannot be assigned” switch is switched off.
...
Setting the “Resource active” switch
When this switch is on, the resource cannot be assigned to tasks, even if his resource skills are correctly set.
...
3. Make sure the “Resource active” switch is switched on.
When this switch is off, the resource cannot be assigned to tasks, even if his resource skills are correctly set:.
...