The purpose of this tool is to facilitate entering interval Order or Task dates into multiple orders.

...

As you continue pasting into the date fields, the dates with be pasted according to the interval you set.

...

The result when “Skip over weekends” is

...

On

Orders/tasks will not be scheduled on weekend days

Weekend days will have a purple frame to differentiate them from weekdays

...

Weekends will be skipped when pasting the dates

...

The result when “Skip over weekends” is

...

Off

Orders/tasks will not be scheduled on weekend days

Weekends will be skipped when pasting the dates

...

Weekend days will have a purple frame to differentiate them from weekdays

...

Date frame colors