The Previous task field determines which task /s or tasks must be completed for a current task to be indicated as ready.
The resource assigned to the task can only start working on his their task when it’s indicated as ready, meaning the Previous task/s has been completed because only . Only then , will all required assets and OOONA tool (in integrated systems), necessary to complete the task will be available for the resource within the order.
...
In “My tasks” page and in other pages, this column will indicate if previous task/s has been completed, meaning the current task is ready to be started:
...
Multiple Previous tasks selection
To select multiple previous tasks for a current task, click the Previous task field and select the required tasks:
...