The Previous task field determines which task/s must be completed for a current task to be indicated as ready.
The resource assigned to the task can only start working on his task when it’s indicated as ready because only when the task is indicated as ready, meaning Previous task/s completed, all required assets, and OOONA tool in integrated systems, will be available for the resource.